A master service agreement (MSA) sets recurring visits and unit prices for corridor and site maintenance. Clear Ground covers brush clearing at $2,000–$5,200 per acre and repair digs at $5–$40 per linear foot, with photo-logged visits. We answer the same business day.
Scopes and background are on energy and utility site work. New-build solar work is on solar site prep.
| What is covered | Pricing basis | Response |
|---|---|---|
| Recurring brush clearing and mulching along corridors and around sites | $2,000–$5,200 per acre; cycle set in the agreement | We answer the same business day; Most jobs start 1–3 weeks after approval |
| Substation and site clearing, grubbing | $3,000–$8,500 per acre | We answer the same business day; Most jobs start 1–3 weeks after approval |
| Repair and utility digs | $5–$40 per linear foot | We answer the same business day; Most jobs start 1–3 weeks after approval |
| Erosion control checks and repairs | Priced from your SWPPP plan sheets | We answer the same business day |
| Unscheduled call-outs | Time and equipment at the rate card | We answer the same business day |
Prices reviewed: September 2026. Ranges for Austin and Central Texas; your site walk sets the final number.
Rates, cycle frequency and term are written into the agreement.
Energized line clearance goes to line crews qualified under OSHA 1910.269 and ANSI Z133. Our work is ground-level clearing, access, trenching and site work, done where your utility's vegetation and safety rules allow it.
Sites covered by the TCEQ Construction General Permit TXR150000 must reach final stabilization at 70% of native background vegetative cover. We keep photo logs that show progress toward it. We prepare the seedbed; seeding is subcontracted.
Last reviewed: September 2026.
Recurring clearing visits, repair digs and erosion control checks at agreed unit prices. Cycle, term and rates are written into the agreement.
By unit: brush clearing $2,000–$5,200 per acre, site clearing $3,000–$8,500 per acre, trenching $5–$40 per linear foot, and erosion control priced from your SWPPP plan sheets.
We answer the same business day. Most jobs start 1–3 weeks after approval.
Send your scope, service area and current cycle. We answer the same business day. Written quote within 48 hours of the site walk.
Request an MSA DiscussionRegistered on Avetta and ISNetworld · Texas