Central Texas Data Center Resource

Who is building Central Texas data centers: 12.1 million sq ft registered since 2023

By Cody Baird, OwnerUpdated October 18, 2026State filings through October 17, 2026

Eight buildings at Cedar Creek make the biggest data center pipeline in Central Texas. They are filed as EDCAUS and hold 5.26 million sq ft of new shell. Skybox is second with 1.98 million across Hutto and Pflugerville. Then come Capital Land Investments (filed as Edged Energy, Maxwell) at 0.87 million. Lockhart Property (Prime Data Center) has 0.76 million, and DFW33220N (ECX Austin, Cedar Creek) has 0.58 million.

The state does not publish who builds them. The filing names the owner and the architect, not the contractor. This page ranks owners from the filings. It lists builders apart, only where a public source names them on a job.

12.1Msq ft of new data center shell registered since January 1, 2023
$13.7Bestimated cost on all 39 filings, fit-outs included
39filings by 14 owner groups (18 owners of record), in 6 counties
79%of the shell space was registered in 2026 (17 of 39 filings)
Background: Skybox rendering of PowerCampus Austin, Hutto (#02) · skyboxdatacenters.com

Public records, not opinion

Nobody paid to be listed. Everything below comes from public records you can pull yourself. Clear Ground does the land clearing and site prep these jobs start with, but listing ourselves would discredit the list.

Picks

Five names hold most of the shell space filed, and five builders are named in public

Three cuts of the same data. The first ranks owners by new shell square feet. The second lists the buildings whose filed start date has not passed. The third lists every builder a public page ties to a Central Texas job.

Most new shell space

Square feet registered since January 2023

  1. EDCAUS filings, Cedar Creek 5,256,800 sq ft
  2. Skybox projects 1,976,610 sq ft
  3. Capital Land Investments I LP 869,684 sq ft
  4. Lockhart Property, LLC 760,000 sq ft
  5. DFW33220N, LLC 578,000 sq ft

Listed starts still ahead

Owner's start date in the filing, after October 17, 2026

  1. EDCAUS15 and EDCAUS16, Cedar Creek November 2, 2026, 1,182,800 sq ft
  2. Project Longhorn, Bastrop County November 30, 2026, 498,165 sq ft
  3. Colovore, Hutto December 1, 2026, 192,694 sq ft
  4. Skybox Hutto 4 January 20, 2027, 846,300 sq ft

A builder named in public

Only where a public page says so

  1. DPR and Sundt Milam County, per DPR. Match to the filing unconfirmed.
  2. HITT Contracting Rowan's Temple campus, per HITT
  3. M.C. Dean Milam County, multi-prime, per DPR
  4. Sendero Industries Hutto utilities, per Sendero
  5. Whiting-Turner Client line only. Not named as GC.

The owner ranking

Two programs hold 60 percent of the new shell space filed

Owners rank by new shell square feet registered with the state. Each name is the owner of record as filed, except two programs grouped by project-name prefix (see Method). Click a name for the profile.

Owners ranked by new data center shell registered with TDLR TABS, January 1, 2023 to October 17, 2026
#Owner, as filed (two rows grouped)New shell, sq ftEst. cost, shell filingsShell + fit-out filingsCounty
1EDCAUS filings, Cedar CreekOwners of record: Burr Computer Environment Inc and Uppingham Adams Holdings, LLC5,256,800$5.40B8 + 0Bastrop
2Skybox projectsOwners of record: four LLCs, listed in the profile1,976,610$1.06B5 + 7Travis, Williamson
3Capital Land Investments I LPFiled as Edged Energy-Austin, Maxwell869,684$2.80B1 + 0Caldwell
4Lockhart Property, LLCFiled as Prime Data Center AUS-01, Lockhart760,000$400M1 + 0Caldwell
5DFW33220N, LLCFiled as ECX Austin, Cedar Creek578,000$440M1 + 0Bastrop
6Milam County Data Center LLCFiled as Freebird Data Center Phase 1, Burlington548,950$470M1 + 0Milam
7Rowan Digital InfrastructureFiled as AUS02, Temple500,000$780M1 + 0Bell
8Individual owner of recordFiled as Project Longhorn, Bastrop County498,165$366M1 + 0Bastrop
9Sabey Data CentersRound Rock400,000$95M1 + 5Williamson
10Switch, LtdRound Rock268,600$40M2 + 1Williamson
11Colovore Austin 1, LLCHutto192,694$280M1 + 0Williamson
12Polmer LLCTemple145,000$197M1 + 0Bell
13OppidanTemple61,554$31M1 + 0Bell
14Individual owner of recordFiled as Arbok, Rockdale40,000$75M1 + 0Milam

Counts projects of $20M or more in Bastrop, Bell, Caldwell, Hays, Milam, Travis and Williamson counties. Square feet and cost are as the owner filed them. Fit-outs add to the filing count, never to square feet. Totals: 12,096,057 sq ft of shell in 26 shell filings, and 39 filings including fit-outs.

Where and when

Bastrop County holds 52 percent of the shell space, and 2026 holds 79 percent

Cedar Creek sits in Bastrop County, and its eight EDCAUS buildings alone are 5.26 million sq ft. Most of the volume arrived this year.

New data center shell by county
CountyNew shell, sq ftShell filingsEst. cost, all filingsWhere
Bastrop6,332,96510$6.21BCedar Creek (EDCAUS, ECX Austin, Project Longhorn)
Williamson2,689,4048$2.61BHutto (Skybox, Colovore), Round Rock (Sabey, Switch)
Caldwell1,629,6842$3.20BMaxwell (Edged), Lockhart (Prime)
Bell706,5543$1.01BTemple (Rowan, Polmer, Oppidan)
Milam588,9502$545MBurlington, Rockdale
Travis148,5001$171MPflugerville (Skybox Austin)
Hays00$0No data center filing of $20M or more
Registrations by year (2026 runs through October 17, 2026)
Year registeredNew shell, sq ftAll filings
2023598,2305
20241,128,08010
2025784,5547
20269,585,19317

Counties as filed. One Skybox filing lists a Pflugerville address under Williamson County; we keep the county on the filing. The Austin metro here is Bastrop, Caldwell, Hays, Travis and Williamson. Bell and Milam are added because Temple and Burlington sit on the same corridor.

Top owners

The top six owners, filing by filing

Each profile quotes the filing: square feet, cost, dates and architect, as filed. Where a filing names no parent company, we do not supply one.

#01 / 14

Cedar Creek, Bastrop County · registered May to September 2026

EDCAUS filings
5.26 million sq ft of shell

Eight buildings, filed between May 26 and September 14, 2026, all on FM 535 at Cedar Creek. Four are 730,000 sq ft. Two are 591,400. Two are 577,000. Each is listed at $600M to $700M.

The filings name two owners of record, Burr Computer Environment Inc and Uppingham Adams Holdings, LLC, and one architect, Gensler. Baxtel, a data center tracker, reported on June 3, 2026 that EdgeConneX filed EDCAUS11 and EDCAUS12 (Baxtel). That report covers only EDCAUS11 and 12. It does not cover the other six, including EDCAUS31 and 32, which sit under a different owner of record. The filings do not name EdgeConneX, so the owners of record stay as filed. We group the eight because they share one project-name code.

Shell sq ft
5,256,800 in 8 buildings
Est. cost
$5.40B, as filed
Listed start
June 30, 2026 to November 2, 2026
Listed finish
to March 31, 2029
Architect
Gensler
Trade report
Baxtel, June 3, 2026
Filings
2026021187 2026021191 2026028410 2026028423 2027000881 2027001020 2026028550 2026028609
Image
Satellite view of FM 535 at Cedar Creek, October 10, 2026. Contains modified Copernicus Sentinel data 2026. The EDCAUS and ECX Austin filings list addresses on this stretch. Pale areas are bare ground and roofs. We do not mark which building is which filing.
Satellite view of FM 535 at Cedar Creek in October 2026: large pale areas of bare ground and big roofs beside the highway, homes to the southwest.Satellite, Oct 10, 2026: Copernicus Sentinel-2

#02 / 14

Hutto and Pflugerville · registered October 2023 to September 2026

Skybox projects
1.98 million sq ft of shell

Twelve filings: five new shell buildings and seven fit-outs. The shells are Hutto 1 (253,730 sq ft), Hutto 2 (235,730), Hutto 3 (492,350), Hutto 4 (846,300) and Austin 2 in Pflugerville (148,500). Hutto 4 was registered September 30, 2026, with construction listed from January 2027 to October 2028.

Every project title carries the Skybox name. The owner of record changes by building. The four are Hutto Data Center Campus, LLC; Hutto Data Center 3, LLC; Austin Data Center 1, LLC; and Austin Data Center 2, LLC.

Skybox's own site lists PowerCampus Austin in Hutto at 600 MW on 160 acres. It also describes Skybox Powered by Prologis as a joint venture.

Shell sq ft
1,976,610 in 5 buildings
Est. cost
$2.16B on all 12 filings, $1.06B on the shells
Architect
Corgan
Latest filing
Hutto 4, core and shell
Owner site
skyboxdatacenters.com

#03 / 14

Maxwell, Caldwell County · registered May 4, 2026

Capital Land Investments I LP
One filing, 869,684 sq ft

A ground-up, one-level building with a data center inside, at 11255 Highway 142 in Maxwell. The filing lists $2.8B, the highest in the set. It lists a start of June 1, 2026 and a finish of June 30, 2028.

The project is filed as Edged Energy-Austin. The owner of record is Capital Land Investments I LP. Beyond the name, we found no filing or announcement that ties the two, so we rank the owner of record.

Shell sq ft
869,684
Est. cost
$2.80B, as filed
Architect
MG2 Architecture Corporation
Status
Review Complete
Filing
TABS2026019322
Image
Satellite view along Highway 142 near Maxwell, October 10, 2026. Contains modified Copernicus Sentinel data 2026. The filing lists 11255 Highway 142. We do not mark which site is the filing.
Satellite view along Highway 142 near Maxwell in October 2026: a large pale site with buildings beside the highway, fields around it.Satellite, Oct 10, 2026: Copernicus Sentinel-2

#04 / 14

Lockhart, Caldwell County · registered May 5, 2026

Lockhart Property, LLC
Two buildings, 760,000 sq ft

Two new 380,000 sq ft shell buildings for future use as data centers, filed as one project on Bob White Road in Lockhart. Cost is listed at $400M. The filing lists a start of June 1, 2026 and a finish of September 30, 2027.

The project title reads Prime Data Center AUS-01. The owner of record is Lockhart Property, LLC.

Prime Data Centers' own Austin page shows a Lockhart campus it calls AUS01: eight buildings on 205 acres, the first at 3300 FM 2720. The filing lists 1395 Bob White Road. The rendering is Prime's.

Shell sq ft
760,000
Est. cost
$400M, as filed
Architect
Gensler
Filing
TABS2026019473
Owner site
Prime: Austin campus AUS01

#05 / 14

Cedar Creek, Bastrop County · registered July 14, 2025

DFW33220N, LLC
One two-story building, 578,000 sq ft

A two-story data center at 8001 Wolf Lane, at FM 535 in Cedar Creek. Cost is listed at $440M, start August 1, 2025, finish June 14, 2026. The filing status is Review Complete.

The project title reads ECX Austin, and the facility is AUS02 at 6752 FM 535. EdgeConneX's own Austin data sheet lists its campus at that address, with buildings AUS01 to AUS04. Construction Equipment Guide reported EdgeConneX starting a data center of the same size, cost and dates. The filing itself does not name EdgeConneX, so the owner of record stays DFW33220N, LLC here.

Shell sq ft
578,000
Est. cost
$440M, as filed
Architect
Gensler
Owner document
EdgeConneX Austin data sheet
Trade report
Construction Equipment Guide
Filing
TABS2025023484
Image
USDA NAIP aerial from 2022 of 8001 Wolf Lane and 6752 FM 535: brush, pasture and a substation. The filing lists a start of August 1, 2025. Compare the 2026 satellite view in #01.
Aerial photo from 2022 of FM 535 at Wolf Lane, Cedar Creek: brush and pasture north of the highway, a fenced substation, homes to the south.Aerial, 2022: USDA NAIP via TxGIO

#06 / 14

Burlington, Milam County · registered April 15, 2026

Milam County Data Center LLC
Freebird Phase 1, 548,950 sq ft

A single-story data center with four data halls, a loading dock and administrative areas, on County Road 133 in Burlington. Cost is listed at $470M, with a start of October 20, 2025 and a finish of October 15, 2026.

The tenant field names Open AI. The architect is Corgan. DPR's project page for a Milam County Data Center in Burlington names DPR and Sundt as contractors. We match that page to this filing by name and town only. No source says they are the same project, so the builders section marks it unconfirmed.

Shell sq ft
548,950
Est. cost
$470M, as filed
Architect
Corgan
Tenant field
Names Open AI
Filing
TABS2026017746
Image
Satellite view of the Burlington area, October 7, 2026. Contains modified Copernicus Sentinel data 2026. It shows a solar farm and a large area of bare ground. The filing lists County Road 133 with no street number, so we do not mark a building.
Satellite view of the Burlington area, Milam County, in October 2026: a large pale area of bare ground beside rows of solar panels and farm fields.Satellite, Oct 7, 2026: Copernicus Sentinel-2

Owners 7 to 14

Eight smaller owners fill out the list

Each card has one image: the owner's own picture where it published one, otherwise a satellite or aerial view of the filed address, dated and credited.

A Rowan and HITT groundbreaking banner in front of a group holding shovels, with an excavator and a truck behind them.

Rowan Digital Infrastructure

Temple, Bell County · #07

500,000 sq ft, $780M. Filed as AUS02 on Bob White Road, registered July 24, 2026. One story, steel frame and precast. No architect is listed on the filing. Builder, per HITT's own page: HITT Contracting. TABS2026026121

Groundbreaking at Rowan's Temple campus, from Rowan's Temple page. The banner names HITT, the builder per HITT's own page.

Photo: rowan.com
Satellite view near Earl Callahan Road and Walter Hoffman Road in October 2026: brush, pasture and scattered homes.

Individual owner of record, Project Longhorn

Bastrop County · #08

498,165 sq ft, $366M. Building One of a new campus near Earl Callahan Road, registered October 7, 2026. The scope lists civil site work, structural and MEPF trades, and a pre-engineered metal building. Gensler is the architect. The owner of record is an individual, named on the filing. TABS2027002962

Satellite view near Earl Callahan Road and Walter Hoffman Road, October 10, 2026. The filing lists a start of November 30, 2026. Contains modified Copernicus Sentinel data 2026.

Satellite: Copernicus Sentinel-2
Sabey Data Centers building at dusk, lit entrance with the Sabey sign, parking lot in front.

Sabey Data Centers

Round Rock · #09

One shell filing of 400,000 sq ft ($95M), Building B at 1300 Louis Henna Blvd, plus five fit-out filings for data halls. Registered October 2024 and October 2025. Corgan is the architect. sabey.com

Sabey's photo of Building A on its Round Rock campus, from its October 2024 completion release. The filing counted here is Building B.

Photo: Sabey Data Centers, via tradeandindustrydev.com
Switch image of a large single-story data center building at The Rock campus.

Switch, Ltd

Round Rock · #10

Two shell filings on Dell Way: 196,000 sq ft (2023) and 72,600 sq ft (2026), each listed at $20M, plus one tenant improvement. The 2026 filing lists construction through June 2028.

Switch's image of The Rock, which Switch places at Dell Technologies' headquarters. The filings are on Dell Way, Round Rock.

Image: switch.com
Colovore aerial rendering of a data center building beside a highway, with homes beyond.

Colovore Austin 1, LLC

Hutto · #11

192,694 sq ft, $280M. A one-story building on Innovation Boulevard, registered September 2, 2026, with a listed start of December 1, 2026. Colovore's site lists Austin as a market. colovore.com

Colovore's Austin rendering, from its Austin page, which names its Hutto site.

Rendering: colovore.com
Satellite view around Eberhardt Road, Temple, in October 2026: large white roofs in an industrial park, a highway to the east.

Polmer LLC

Temple, Bell County · #12

145,000 sq ft, $197M. A single-story building on Eberhardt Road, registered December 15, 2025. No architect is listed. TABS2026008019

Satellite view around 2230 Eberhardt Road, Temple, October 10, 2026. Contains modified Copernicus Sentinel data 2026.

Satellite: Copernicus Sentinel-2
Aerial photo from 2022 around Eberhardt Road, Temple: a large graded site, industrial buildings and a road grid.

Oppidan

Temple, Bell County · #13

61,554 sq ft, $31M. A 5 MW data center with one data hall, registered March 28, 2025. Salas O'Brien is the architect. TABS2025015318

USDA NAIP aerial from 2022 around 2313 Eberhardt Road, Temple, before the March 2025 filing.

Aerial: USDA NAIP via TxGIO
Satellite view around Charles Martin Hall Road, Rockdale, in October 2026: large industrial roofs and pads beside a lake.

Individual owner of record, Arbok

Rockdale, Milam County · #14

40,000 sq ft, $75M. Filed as an addition to an existing building, status Project Closed. The owner of record is an individual, named on the filing. TABS2026009518

Satellite view around 2721 Charles Martin Hall Road, Rockdale, October 7, 2026. The filing is an addition to an existing building. Contains modified Copernicus Sentinel data 2026.

Satellite: Copernicus Sentinel-2

Builders directory, alphabetical

Public sources name five builders on a new Central Texas data center site, and none for most owners

This directory is not ranked. A firm appears next to a project only where a public page says so, and each entry links that page. The state filing has no contractor field, so a missing name means no public source, not a quiet job.

The public sources: DPR Construction's Milam County Data Center page, the Cameron Industrial Foundation's outreach notice, HITT Contracting's Project Temple page and Sendero Industries' 600MW Data Center page.

01 / 05

Burlington, Milam County · joint venture

DPR Construction and Sundt Construction
Named by DPR's own page

DPR's project page says the two firms, as a joint venture, are the contractors on the Milam County Data Center under construction in Burlington. The Cameron Industrial Foundation listed a January 20, 2026 outreach event for local subcontractors. The scopes open to local firms were final clean, glazing supply, flooring, signage, fencing, landscaping, millwork, catering and security.

Unconfirmed: we match this page to the Milam County Data Center LLC filing by name and town. No source we found says Freebird is the same project. Sundt's own site has no page for this project that we found, so Sundt's role rests on DPR's page.

Public source
DPR Construction, Milam County Data Center project page
Outreach event
Cameron Industrial Foundation, Business Outreach Event with General Contractor, posted Jan 8, 2026
Also on record
One City of Austin permit for data center MEP work, 2025 (see the City permits below)
Websites
dpr.com · sundt.com
Image
DPR's photo of Vantage Data Centers' CA2 campus in Santa Clara, California, from its Advanced Technology page. It is not the Burlington job.
Exterior of a multi-story data center building with a row of generator exhaust stacks: Vantage Data Centers' CA2 campus in Santa Clara, from DPR's Advanced Technology page.Photo: Dan Peak Photography, via dpr.com

02 / 05

Temple, Bell County · general contractor, per its site

HITT Contracting
Named by HITT's own page

HITT's project page says it is delivering Rowan Digital Infrastructure's 300 MW hyperscale campus in Temple, on 700 acres, with substantial completion targeted for 2027. It names Rowan as the client and HKS as the A/E consultant.

The AUS02 filing names Rowan as the owner of record in Temple. We match the two by owner and town. Rowan's own Temple photo shows a groundbreaking banner with HITT's name (in the owners section above).

Public source
HITT Contracting, Project Temple project page
Client, per HITT
Rowan
Owner filing
AUS02, Temple
Website
hitt.com
Image
HITT's photo of the Project Temple groundbreaking, from its Temple project page.
Seven people in hard hats and vests holding shovels behind a Rowan and HITT Project Temple groundbreaking banner, an excavator and a truck behind them.Photo: hitt.com

03 / 05

Burlington, Milam County · systems integrator

M.C. Dean
Multi-prime on the same project

DPR's page lists M.C. Dean as a multi-prime contractor on the Milam County Data Center. It describes the role as design-build systems integrator for lighting, power, lightning protection and security systems, plus modular power solutions.

The page gives no size, megawatts or owner. The same unconfirmed match to the Freebird filing applies.

Public source
DPR Construction, Milam County Data Center project page
Website
mcdean.com
Image
M.C. Dean's logo, from its site. We found no data center project photo there.

04 / 05

Houston, TX · civil contractor

Sendero Industries
Utilities on the Hutto campus

Sendero's own project page covers onsite utilities at Skybox PowerCampus Austin in Hutto, a 158-acre site. The scope includes 4,115 ft of 24-inch storm pipe, 1,346 ft of 8-inch sanitary sewer and 9,787 ft of 12-inch water main. It counts 21 hydrants.

Sendero calls itself a Houston-based civil contractor. It does site prep, earthwork, drainage and utilities, and it lists Whiting-Turner as the client on this job.

Public source
Sendero Industries, 600MW Data Center project page
Client, per Sendero
Whiting-Turner
Website
senderoindustries.com
Image
Satellite view around 4200 and 3399 County Road 132, Hutto, the addresses on the Skybox Hutto filings, October 10, 2026. Contains modified Copernicus Sentinel data 2026. Sendero's page covers onsite utilities on this campus. We do not mark which building is which.
Satellite view of County Road 132 at Hutto in October 2026: large pale roofs and paved yards beside a highway, farm fields and a subdivision around them.Satellite, Oct 10, 2026: Copernicus Sentinel-2

05 / 05

General contractor, per its site

The Whiting-Turner Contracting Company
Named as a client, not as the builder

Sendero's page lists Whiting-Turner as its client for the Hutto utilities. That is the only public mention we found tying the firm to the Skybox campus.

No public source we found names Whiting-Turner as the general contractor on any filing here, so we do not say it is. It stays in this directory so a reader can see the lead and the gap.

Public source
Sendero Industries, 600MW Data Center project page (client line)
General contractor on record
None found
Website
whiting-turner.com
Image
From Whiting-Turner's Mission Critical page. Not a Central Texas job.

City of Austin building permits since 2023

Seven firms appear on City of Austin data center permits, nearly all for work inside existing buildings

The City records a contractor of record on its permits, and 12 of these 13 name one. Most of the corridor is outside the City. Twelve permits are remodels, fit-outs or equipment work, and one is a new pad for a modular unit.

Alterman Inc

1 City of Austin permit

Upgrade of a dual feed to a corporate data center, February 2024. 2024-010770

Burk General Contractors LLC

1 City of Austin permit

Remodel of an existing data center and admin office areas at Metro Center Drive, August 2023. Austin-based, per its site. 2022-072978

CM Constructors

4 City of Austin permits

Four permits, 2023 to 2024: interior fit-outs and added power and cooling at an existing data center, and electrical connections for UPS. Offices in Austin, San Antonio and Grapevine, per its site. 2023-075434 2023-036314 2024-004218 2022-071936

DPR Construction

1 City of Austin permit

Mechanical, electrical and plumbing for a data center added inside an existing client facility, July 2025. 2025-090060

Mission Critical Facilities International

2 City of Austin permits

Two permits, December 2024: cooling units in an existing data center, upper and lower floors. 2024-151690 2024-151689

Novo Construction

2 City of Austin permits

A data hall remodel (October 2025) and a new exterior pad for a modular data center foundation at 811 Clayton Lane (March 2026), the only new construction among the 13. 2025-119435 2026-036762

Southland Industries

1 City of Austin permit

Generator and split-system air conditioning for a data center building, November 2023. Mechanical contractor; its site lists data centers as a market. 2023-016696

Source: City of Austin issued construction permits, building permits only. Download the 13 permits (CSV). Not listed: large national builders we could not tie to a specific Central Texas data center with a public source.

Method

How we ranked them: state filings, not press releases

The ranking uses one public source anyone can re-run: the Texas Department of Licensing and Regulation's accessibility project registry (TABS).

  • What counts. A data center filing registered from January 1, 2023 to October 17, 2026, estimated at $20M or more, in Bastrop, Caldwell, Hays, Travis, Williamson, Bell or Milam County.
  • How we found them. The search has no project-type filter. We pulled all 590 filings of $20M or more from 11,840 registered in those counties, and read each detail page. A filing counts when its name, scope, owner or tenant says data center.
  • The rank. New shell square feet, as filed. New construction and additions count as shell. Fit-outs inside an existing building count toward filings and cost, never square feet.
  • Owners. The owner of record as filed. Where one program files under several LLCs and its project names share a prefix (Skybox, EDCAUS), we group them and list every entity. We name a parent company only where a filing or the owner's own page ties it.
  • Individuals. Where the owner of record is a person, we write individual owner of record and leave the name on the state filing.
  • Not used. Ratings, safety records, press mentions, price and paid placement. Clear Ground publishes this list and does not rank itself.

Download the filings (CSV)

Limits

A filing is a registration, not proof of a building

  • TABS is an accessibility review. It registers a project for review. It is not a building permit, and it does not show that work started or finished.
  • Cost and size are the owner's estimate. One filing, such as the $2.8B Maxwell building, can move a rank on its own.
  • The $20M floor and the wording. Smaller edge sites are out. A project that never says data center in its filing is out. A few filings mention servers or power without saying it. We read them and left them out.
  • LLC names hide the brand. Several owners of record are single-purpose companies. We do not guess who stands behind them.
  • No contractor field. The state names the owner and the architect. Builders come from separate public pages, one claim at a time.
  • ERCOT's report is not out. ERCOT and the PUC plan a data center report on or before December 10, 2026. Until then there is no public megawatt count by developer.
  • Re-filed projects. A project can be filed twice or carry inconsistent fields. We count filings as filed. Sabey data hall B35 was filed in 2024 and again in 2025, and the Hutto 1 filing lists 253,730 sq ft where its scope says 235,730.
  • Corrections. Email a source and we fix it.

Our services

We also provide land clearing, excavation, site prep and demolition

Every project on this page starts with cleared, graded ground.

What's next

Three things will change this page before spring

  • ERCOT and PUC report. Due on or before December 10, 2026. ERCOT's request asks developers for ownership and controlling interests, so it may name owners behind the LLCs. We check it on December 11.
  • Quarterly TABS pull. We re-run the same pull each quarter and republish the CSV. The next one is January 2027.
  • City portals. Building permits in Hutto, Round Rock, Temple, Taylor and Lockhart name contractors. Builders are added as the permits name them.

Common questions

Central Texas data centers, answered

Who is building the most data center space in Central Texas?

By new shell square feet registered with the state since January 2023, the eight EDCAUS buildings at Cedar Creek lead with 5,256,800 sq ft. Skybox is second with 1,976,610. The owner of record on the EDCAUS filings is a pair of companies, and the filings do not say who is behind them.

How much data center space is registered in Central Texas?

The state has 39 data center filings of $20M or more in the Austin metro plus Bell and Milam counties since January 1, 2023. 26 are new shell, totaling 12,096,057 sq ft. Estimated cost across all 39 filings is $13.7B.

Who is the general contractor on a given Central Texas data center?

For most, no public source says. The state filing has no contractor field. DPR's page names DPR and Sundt as the contractors on a Milam County Data Center in Burlington. HITT's page says it is delivering Rowan's Temple campus. Sendero's page lists Whiting-Turner as its client on the Hutto utilities. We do not call Whiting-Turner the general contractor.

Does a state filing mean a data center is being built?

No. TABS registers a project for accessibility review. The dates, cost and square feet are the owner's estimate, and the filing does not show that construction started.

Why are so many owners LLCs?

Developers often hold each building in a single-purpose company. We show the owner of record as filed and name a parent company only where a filing or the owner's own announcement ties it.

Can a company pay to be on this list?

No. The ranking comes from state filings, and the directory comes from public pages.

How often is this page updated?

Every quarter, from the same state pull, and again when ERCOT and the PUC publish their data center report, due on or before December 10, 2026.

Working on a Central Texas site?

Bidding a data center site package?

Send us the plans. We scope every project in person before quoting. If we are not the right fit, we will say so.

Request a quote

Austin, the Texas Hill Country and Central Texas